SOLUTION AT Australian Expert Writers

Activities & preds. are the same as in the PowerPoint but the durations are different. You are required to draw an AON diagram filling in the boxes with all the necessary information as in the PowerPoint. Work out the CP [critical path]’
All the ES-EF lines I call horizontal and ES-LS or EF-LE lines vertical. When you determine the CP route, examine the figures in the horizontals and verticals. Do you notice the difference on the CP-route verticals from the non-CP verticals?
Activity predecessor Duration
a – 10 days
b -. 8
c a 6
d a 8
e a 12
f b,c 8
g d 10
h d,e 12
i f 12
j g,h 8